Phase 1 and Phase 2 Crude Oil Terminals at Qinhuangdao Port

更新时间:2018-04-23 16:03:19点击次数:1005次
Phase 1 terminal has two berths for handling of crude oil on ships up to 20 000 DWT at rate of 10 mtpa. The wharf of caisson dolphin strucuter, in length of 278.5 m, is connected to shore by a trestle in length of 435.2 m. Phase 2 terminal has included th
相关介绍

Phase 1 terminal has two berths for handling of crude oil on ships up to 20 000 DWT at rate of 10 mtpa. The wharf of caisson dolphin strucuter, in length of 278.5 m, is connected to shore by a trestle in length of 435.2 m. Phase 2 terminal has included the construction of one berth in length of 322.5m for ships up to 50 000 DWT, a breakwater in length of 1 074m, a tank farm of 50 000 m3 storage capacity.




Copyright © 2009 fdine.com.cn All Rights Reserved CCCC FIRST HARBOR CONSULTANTS CO., LTD. Copyright

Address: Fdine Tower, 18 Dongting Road, Hexi District, Tianjin, China     P.C:300222      Email:fdine@fdine.com.cn

Tel:022-28160808     FAX:022-28341925     

ICP Record:津ICP备11004384号-1      津公网安备 12010302002235号         Powered by:comkeji

Rong Xiu Home

GangGong TEC

津公网安备 12010302002235号